Sound Isolation and Noise Control
The achievement of a quiet environment is a prerequisite for creating the ideal acoustical environment for concert halls or other facilities. Nagata Acoustics have two categories of objectives: 1) the achievement of sound isolation from external sounds and vibrations (such as adjacent traffics), and from other activity spaces within the structure; and 2) the control of noise from HVAC system and other mechanical apparatus within the structure.
Outline of Service Phases
1. Programming
- Studies on acoustical goal
- Noise and vibration survey of site
- Intensive workshop sessions
2. Schematic Design and Design Development
- Acoustical check of planning and room arrangement
- Acoustical check of building materials and structures
- Calculation of acoustical parameters
- Noise control and specifications for HVAC system
3. Construction
- Finalize construction documents
- On-site inspection
- Acoustical check with measurements